The National High Speed Rail Corporation Limited (NHSRCL) signed a contract agreement with Sojitz and L&T consortium for executing electrical works under the EW-1 package for the Mumbai-Ahmedabad high speed rail corridor project.
The National High-Speed Rail Corporation Limited (NHSRCL) has achieved another milestone in the Mumbai-Ahmedabad High-Speed Rail Corridor project by successfully completing the construction of 100 km of viaduct, and 250 km of pier work.
The National High Speed Rail Corporation Limited (NHSRCL) has completed the 100 per cent land acquisition in Gujarat for the Mumbai-Ahmedabad bullet train project.
The National High-Speed Rail Corporation Limited (NHSRCL) achieved a significant milestone by successfully erecting the first steel bridge, spanning an impressive 70 metres in length, across National Highway 53 in Surat, Gujarat.
The National High-Speed Rail Corporation Limited (NHSRCL) announced the successful completion of the fifth river bridge on the MAHSR corridor, situated over the Auranga River in the Valsad district of Gujarat.
The National High-Speed Rail Corporation Limited (NHSRCL) has successfully constructed these crucial infrastructures, marking another milestone in the development of this ambitious project.
The National High-Speed Rail Corporation Limited (NHSRCL) signed a contract with M/s Afcons Infrastructure Limited on Thursday for the construction of a 21 km long tunnel. The major part of this contract is to construct India's first 7 km long undersea rail tunnel in Maharashtra for Mumba
As per the official statement of National High-Speed Rail Corporation Limited (NHSRCL), it is envisaged that only trained and certified engineers/work leaders are to work at the site for track construction works.
A 320-metre-long river bridge on the Mumbai Ahmedabad High-Speed Rail Corridor (MAHSRC) is being built by the National High-Speed Rail Corporation Limited (NHSRCL).
The BKC station will have six platforms and the length of each platform is nearly 415 m (sufficient to accommodate a 16-coach bullet train). The station will have connectivity with the Metro and road. Bandra Kurla Complex station is the only underground station on the Mumbai Ahmedabad bullet
The managing director of National High-Speed Rail Corporation Limited (NHSRCL), Rajendra Prasad, on Wednesday said that the company will try to run bullet trains in Gujarat by August 2027.