Prime Minister Narendra Modi visited the under-construction Bullet Train Station at Surat in Gujarat on Saturday and reviewed the Progress of the Mumbai-Ahmedabad High-Speed Rail Corridor
Earlier in the day, the Prime Minister landed in Surat to visit the under-construction Bullet Train Station, reviewing the progress of the Mumbai-Ahmedabad High-Speed Rail Corridor (MAHSR).
New Delhi [India], April 9: The Mumbai-to-Dubai dream of commuting in a mere two hours is not far away with the planned undersea high-speed rail. The ambitious project, guided by UAE's National Advisor Bureau Limited, plans to bridge India and the UAE using an underwater train, Dubai. If rea
Mumbai (Maharashtra) [India], December 9: India's urbanization is at a turning point, marked by a surge in rural-to-urban migration. This drives the expansion of existing urban nodes, towards areas along their peripheries. 40% of India's population, equivalent to 60 crore people, is expected
In a key milestone for the Mumbai-Ahmedabad Bullet Train project, the construction of the bridge over the Kolak River in Valsad district, Gujarat, has been successfully completed. This advancement marks another step forward in the development of India's first high-speed rail corridor.
The National High Speed Rail Corporation Limited (NHSRCL) signed a contract agreement with Sojitz and L&T consortium for executing electrical works under the EW-1 package for the Mumbai-Ahmedabad high speed rail corridor project.
As per the official statement of MAHSR, all civil contracts for Gujarat and Maharashtra have been successfully awarded, showcasing robust project management. Over 120.4 km of girders have been launched, and 271 km of pier casting have been completed, emphasising the rapid progress in critica
The National High-Speed Rail Corporation Limited (NHSRCL) has achieved another milestone in the Mumbai-Ahmedabad High-Speed Rail Corridor project by successfully completing the construction of 100 km of viaduct, and 250 km of pier work.
The National High Speed Rail Corporation Limited (NHSRCL) has completed the 100 per cent land acquisition in Gujarat for the Mumbai-Ahmedabad bullet train project.
The National High-Speed Rail Corporation Limited (NHSRCL) achieved a significant milestone by successfully erecting the first steel bridge, spanning an impressive 70 metres in length, across National Highway 53 in Surat, Gujarat.