"BMC's ambitious Mumbai Coastal Road Project successfully installed a second large Bow Arch String Girder connecting the Mumbai Coastal Road and the Bandra-Worli Sea Link in the early hours of today, May 15, 2024. The work began at 3 am and was completed at 6:07 am," BMC said.
The ambitious Mumbai Coastal Road (MCR) project, spearheaded by the Brihanmumbai Municipal Corporation (BMC), achieved a significant milestone on Friday with the BMC successfully installing the first bow arch string girder that connects the Coastal Road to the Bandra-Worli Sea Link (BWSL). T
Shiv Sena MLA Aaditya Thackeray raised concerns about the inauguration of the Mumbai coastal road project, alleging that the government is seeking undue credit for a project that remains incomplete.
Mumbai (Maharashtra) [India], February 26: The city that never sleeps is on the cusp of a significant transformation. The much-anticipated and ambitious Coastal Road project, a state-of-the-art expressway stretching along Mumbai's western coastline, is poised to be a major game changer, espe
Three accused persons in the case of a suspicious boat found near Gateway of India have been remanded to police custody till February 10, officials said on Wednesday.
Maharashtra CM Eknath Shinde inspected the Coastal Road Project at Priyadarshini Park and said that the project will be completed by January 31.
After the inspection, CM Shinde said, "The first phase is to be completed by 31st January."
The exercise commenced in the early hours of December 8, 2023, and was conducted in two phases over the day. The first phase saw security emergencies such as attacks by terrorists and bomb threats from IEDs.
The Brihanmumbai Municipal Corporation (BMC) will highlight the disaster management measures taken for this project in front of the DRRWG delegates. The DRRWG's five key priorities are early warning, resilient infra, national response, building back better and nature-based solutions, the Min