First mountain tunnel breakthrough in Mumbai-Ahmedabad bullet train corrid
Updated : 2 months, 1 week ago IST
A major milestone was achieved in India's first bullet train corridor with the breakthrough of a high-speed mountain tunnel at Maharashtra's Palghar, Ashwini Vaishnaw, Minister of Railways, said on Friday.
Read More
Gujarat: Railway Minister Vaishnaw and Japan's Minister Nakano inpects bul
Updated : 5 months, 1 week ago IST
India's first 508 km long Bullet Train corridor is being constructed between Mumbai and Ahmedabad. Out of 508 km, 323 km of viaduct and 399 km of pier work have been completed, including 17 River bridges, five PSC (pre-stressed concrete) and nine Steel bridges.
Read More
New Austrian tunnelling method achieves milestone breakthrough in BKC-Shil
Updated : 5 months, 1 week ago IST
In a significant milestone for the ambitious undersea tunnel project between BKC and Shillphata, the New Austrian Tunnelling Method (NATM) has successfully achieved a breakthrough for its 5 km tunnel stretch.
Read More
First full span box girder launched through launching gantry in Maharashtr
Updated : 5 months, 1 week ago IST
The National High-Speed Rail Corporation Limited (NHSRCL) has successfully launched the first full span Pre-Stressed Concrete (PSC) Box Girder of 40 meters length through the full span launching gantry (FSLG) in the Maharashtra section of the Mumbai-Ahmedabad Bullet Train corridor, at Sakhar
Read More
Mumbai-Ahmedabad Bullet Train Corridor: River bridge on Daman River in Guj
Updated : 8 months, 1 week ago IST
According to a release, this is the sixteenth river bridge completed out of the planned 21 river bridges in Gujarat for the project.
Read More
Bullet Train Project casts its first Full Span 40 Mtrs Box Girder for Maha
Updated : 1 year, 1 month ago IST
The National High-Speed Rail Corporation Limited (NHSRCL) has reached a significant milestone in the construction of the Mumbai-Ahmedabad Bullet Train corridor, as it successfully cast its first Full Span Pre-Stressed Concrete (PSC) Box Girder for the Maharashtra section, as per an official
Read More
Railway Minister Ashwini Vaishnaw announces installation of electrical mas
Updated : 1 year, 1 month ago IST
The electrification work for the Mumbai-Ahmedabad Bullet Train corridor began, with the first two steel masts erected on the viaduct at a height of 14m from the ground level in between the Surat-Bilimora Bullet Train Stations in Gujarat.
Read More
Electrification work begins on Mumbai-Ahmedabad bullet train corridor
Updated : 1 year, 1 month ago IST
The electrification work for the Mumbai-Ahmedabad Bullet Train corridor has begun, with the first two steel masts erected on the viaduct at a height of 14m from the ground level in between Surat- Bilimora Bullet Train Stations in Gujarat.
Read More
200,000 noise barriers installed along viaduct of Mumbai-Ahmedabad bullet
Updated : 1 year, 2 months ago IST
The Mumbai-Ahmedabad Bullet Train Project has achieved a significant milestone with the installation of 206,000 noise barriers along both sides of the 103 km viaduct.
Read More
All nine river bridges completed between Vapi and Surat for Mumbai-Ahmedab
Updated : 1 year, 4 months ago IST
The Mumbai-Ahmedabad High Speed Rail (MAHSR) or popularly known as the Ahmedabad-Mumbai bullet train project has marked a major achievement with the completion of all nine river bridges between Vapi and Surat.
Read More
1389.5 hectare land acquired for Mumbai-Ahmedabad bullet train project: Mi
Updated : 1 year, 7 months ago IST
The Mumbai-Ahmedabad bullet train corridor has been making steady progress since work began in November 2021. The project initially faced delays due to challenges in land acquisition.
Read More
Mumbai-Ahmedabad bullet train project: Work on 7-km undersea rail tunnel c
Updated : 1 year, 8 months ago IST
The Mumbai-Ahmedabad bullet train corridor has been making steady progress since work began in November 2021. The project initially faced delays due to challenges in land acquisition.
Read More