PoGB: Investigation reveals major flaws in Bale Gowand hydropower project

Initiated under the 2012 Annual Development Program (ADP) at a cost of Pakistani Rupees (PKR) 395.324 million, the project began construction in 2014 and was completed in 2022. However, just two months after completion, cracks appeared in the power channel and four bays, leading to water leakage and a drop in power generation, Pamir Times reported.

ANI Feb 09, 2025 23:40 IST googleads

Representative Image

Gilgit [PoGB], February 9 (ANI): A recent investigation into the 2 MW Bale Gowand Hydropower Project on the Hoshe River in Pakistan-occupied Gilgit Baltistan, has revealed major issues with its construction and planning, according to a report by Pamir Times.
Initiated under the 2012 Annual Development Program (ADP) at a cost of Pakistani Rupees (PKR) 395.324 million, the project began construction in 2014 and was completed in 2022. However, just two months after completion, cracks appeared in the power channel and four bays, leading to water leakage and a drop in power generation, Pamir Times reported.
A three-member committee, formed under the chairmanship of Engineer Zia-ur-Rehman, visited the site and submitted a detailed report, as reported by Pamir Times.
The investigation revealed that the four bays, which store and direct water to the turbines, were built on soft and unstable ground. This resulted in cracks due to subsidence. Similarly, the spillway was constructed on poor-quality land, contributing to further damage, while the 4,300-foot-long power channel was found leaking water due to cracks in its walls. The report attributes these issues to the use of substandard materials, including a poor cement-water ratio, Pamir Times reported.
Additionally, the feeder channel, relocated 700 feet after the 2015 floods, faces similar instability and water pressure issues. The report suggests urgent repairs and improvements, including rebuilding the four bays on more stable terrain and relocating the spillway to a better-suited location, as reported by Pamir Times.
According to Pamir Times, the investigation also criticizes the contractors, Ahmed Ali and Sons and Ghulam Mehdi and Sons, for their subpar work. Despite the potential for increasing the project's capacity to 6 MW, the report urges authorities to focus on repairing the existing infrastructure instead of expanding power generation.
The report highlights the urgent need for corrective measures to prevent further damage and ensure the project's long-term sustainability. It also calls for a thorough review of the design and construction processes, recommending stricter quality control in future projects to avoid similar failures. (ANI)

Get the App

What to Read Next

Europe

Blasphemy laws in Pakistan target religious minorities: GHRD

Blasphemy laws in Pakistan target religious minorities: GHRD

At the 61st session of the United Nations Human Rights Council, the organisation Global Human Rights Defence (GHRD) raised concerns over the continued misuse of blasphemy laws in Pakistan and their impact on religious minorities.

Read More
Asia

MEA rejects Pakistan’s statement on India-Canada deal

MEA rejects Pakistan’s statement on India-Canada deal

"We reject this statement made by Pakistan on the matter. India's credentials regarding non-proliferation are impeccable and well recognised by the global community. A country with a well-documented history of clandestine nuclear proliferation can hardly preach the virtues of export controls and proliferation risks. Such ludicrous statements are nothing more than an attempt by Pakistan to distract from its own abysmal record," he said.

Read More
Asia

India rejects Pakistan's "baseless allegations"

India rejects Pakistan's

India on Thursday rejected Pakistan's allegations of aggravating skirmishes with Afghanistan, calling them "baseless" and accusing Pakistan of blaming others for its own misdeeds.

Read More
Asia

Policy delays leave Pakistan short of critical medicines

Policy delays leave Pakistan short of critical medicines

Pakistan faces a severe shortage of life-saving medicines, including cancer drugs and vaccines, due to government delays in notifying official prices. While global supply remains stable, regulatory hurdles have stalled legal imports, raising concerns over patient survival and the potential rise of unregulated, counterfeit medicines.

Read More
Asia

Pakistan’s outdated mandi system stifles agricultural innovation

Pakistan’s outdated mandi system stifles agricultural innovation

Pakistan's fruit and vegetable supply remains dominated by traditional middlemen and the "mandi" system, with digital platforms handling only 2-3% of trade. Restrictive provincial laws and lack of infrastructure force farmers into dependency on commission agents, stalling modern technological transformation in the agricultural sector.

Read More
Home About Us Our Products Advertise Contact Us Terms & Condition Privacy Policy

Copyright © aninews.in | All Rights Reserved.