Cascade tripping at MSETCL sub-stations led to power outage in Mumbai on October 12: Tata Power

Mumbai (Maharashtra) [India], October 16 (ANI): The power outage of October 12 in Mumbai was because of cascade tripping at the sub-stations and transmission lines of Maharashtra State Electricity Transmission Company (MSETCL), said Tata Power, assisting a central team in a probe into the matter, on Friday.

ANI Oct 16, 2020 17:58 IST googleads

Representative image

Mumbai (Maharashtra) [India], October 16 (ANI): The power outage of October 12 in Mumbai was because of cascade tripping at the sub-stations and transmission lines of Maharashtra State Electricity Transmission Company (MSETCL), said Tata Power, assisting a central team in a probe into the matter, on Friday.
Tata Power is supporting the team, comprising of the officials from Central Electricity Authority, by providing information and data related to the chain of events in the city on Monday.
On the day of the power outage, Tata Power said that as per its preliminary assessment of the situation, many parts of Mumbai experienced an unforeseen electricity failure in the morning due to the tripping of MSETCL's 400-KV transmission system at Kalwa. There are four incoming lines to MSETCL Kalwa receiving stations for further transmission of power to Mumbai. Out of these four lines, MSETCL's 400-KV Pune-Kalwa line was under forced shutdown since October 10, 2020.
Early on Monday morning, the MSETCL went for an emergency shutdown of another 400-KV Kalwa-Padghe line-1 to attend to a fault and expected to revive it by 9.30 am, but could not, Tata Power said in a release.
"As per the chain of events, with two lines out of service, the third line tripped at 9.58 am. The 400-KV Kalwa-Padghe-2, carrying 644 MW power to the city, tripped. This led to the overloading of the fourth and subsequent tripping at 10.05 am, which led to a sudden load drop and power outage in Mumbai," it added.
Tata Power further said Mumbai's islanding system that saves the city from major power outages was successfully separated at 9.58 am. "However it could not hold a sudden 1,000-MW load drop at 10.05 am. Tata Power rapidly initiated restoration by bringing in power from its three hydro units and activating its Trombay gas and coal units as soon as the MSETCL transmission lines were connected. Simultaneously, Tata Power started restoring supply to its consumers progressively from noon onwards and throughout the course of the day." (ANI)

Get the App

What to Read Next

Politics

Assam CM hands over appointment letters to 5,754 candidates

Assam CM hands over appointment letters to 5,754 candidates

Assam Chief Minister Dr Himanta Biswa Sarma on Thursday distributed appointment letters to 5,754 candidates under the Education and Power Department at a function held at the Veterinary College playground, Khanapara in Guwahati.

Read More
General News

Shinde on bomb threat emails to blow BSE, Vidhan Bhavan

Shinde on bomb threat emails to blow BSE, Vidhan Bhavan

Maharashtra Deputy Chief Minister Eknath Shinde stated that the threats were bogus, calling the Vidhan Bhavan safe and added that operations to tackle the issue are underway smoothly.

Read More
Politics

“NDA Will Form Government in Tamil Nadu”: TTV Dhinakaran in Tiruchirappalli

“NDA Will Form Government in Tamil Nadu”: TTV Dhinakaran in Tiruchirappalli

AMMK General Secretary T T V Dhinakaran said that the National Democratic Alliance (NDA) will come to power in Tamil Nadu, stating that people are dissatisfied with the present government.

Read More
General News

Maharashtra: Green Corridor movement saves life of woman

Maharashtra: Green Corridor movement saves life of woman

The Green corridor between Thane and Mumbai allowed for the organ to leave from Jupiter Hospital in Thane at 13:45 and reach Nanavati Hospital at 14:16, covering a distance of 26 kilometres in just 30 minutes.

Read More
General News

Centre’s natural gas regulation order may impact Karnataka power

Centre’s natural gas regulation order may impact Karnataka power

According to a release, Gas Authority of India Limited (GAIL) has completely stopped the gas supply to the Yelahanka gas-based power plant since March 12, 6:00 am.

Read More
Home About Us Our Products Advertise Contact Us Terms & Condition Privacy Policy

Copyright © aninews.in | All Rights Reserved.