2.7 km long continuous tunnel completed with first breakthrough in 21 km tunnel between BKC and Shilphata

Out of the total 21 km tunnel, 5 km is being constructed using the New Austrian Tunnelling Method (NATM) between Shilphata and Ghansoli, while the remaining 16 km will be built using Tunnel Boring Machines (TBMs). The tunnel also includes a 7 km long undersea section beneath Thane Creek.

ANI Jul 11, 2025 08:11 IST googleads

Screengrab (Photo/@nhsrcl)

Shilphata (Maharashtra) [India] July 11 (ANI): On July 9, the first breakthrough was achieved in the 21 km long tunnel being constructed between Bandra-Kurla Complex (BKC) and Shilphata in Maharashtra, marking the successful completion of a 2.7 km continuous tunnel section.
Out of the total 21 km tunnel, 5 km is being constructed using the New Austrian Tunnelling Method (NATM) between Shilphata and Ghansoli, while the remaining 16 km will be built using Tunnel Boring Machines (TBMs). The tunnel also includes a 7 km long undersea section beneath Thane Creek.
To expedite tunnelling in the NATM portion, an Additionally Driven Intermediate Tunnel (ADIT) was constructed, allowing simultaneous excavation towards Ghansoli and Shilphata sides. So far, about 1.62 km has been excavated from the Shilphata side, and the total progress in the NATM section stands at approximately 4.3 km.

Comprehensive safety measures have been implemented at the site, including ground settlement markers, piezometers, inclinometers, strain gauges, and biometric access control systems to ensure safe and controlled tunnelling activities without disturbing nearby structures.
The work on the Mumbai-Ahmedabad high-speed bullet train project is going on in full swing in Maharashtra, with major structural and tunnelling milestones being achieved, according to the National High-Speed Rail Corporation Limited (NHSRCL) said on Saturday.
According to the NHSRCL, work on all three elevated stations in the state, Thane, Virar, and Boisar, is advancing swiftly, and the first slabs for Virar and Boisar stations have recently been cast. Across the alignment, pier foundations and pier works are underway at various locations, with approximately 44 km of piers cast to date.
In the Palghar district, viaduct construction has also commenced using full-span box girder launching technology, starting from the Dahanu area. Additionally, the excavation of seven mountain tunnels in the Palghar district is actively in progress, demonstrating the project's engineering scale and complexity. Bridge construction has also kicked off at three major rivers: Vaitarna, Ulhas, and Jagani, further contributing to the corridor's critical infrastructure.
An important component of the project is the 21-kilometre-long underground and undersea tunnel connecting the Mumbai Bullet Train station at Bandra-Kurla Complex (BKC) to Shilphata. Of the 21 km tunnel, 16 km is being excavated using Tunnel Boring Machines (TBMs), while 5 km is being executed using the New Austrian Tunnelling Method (NATM). The tunnel includes a 7 km undersea stretch beneath Thane Creek, marking a significant feat in Indian tunnelling history.
So far, approximately 4.1 km of tunnel heading has been achieved through NATM from the Shilphata site, and two concurrent faces have been developed from the ADIT portal. In terms of vertical construction, base slab casting at the Vikhroli shaft (56 meters deep) and Sawli shaft (39 meters deep) has been completed. Additionally, sludge treatment plants are being installed at shaft locations, and the Mahape tunnel lining casting yard is actively producing tunnel lining segments.
For the under-construction Mumbai Bullet Train station at Bandra Kurla Complex, 80% of the excavation work has been completed. Base slab casting at 100 ft below ground level has already started at both ends of the station site, NHSRCL added. (ANI)

Get the App

What to Read Next

General News

ED attaches 31 immovable properties worth Rs 581.65 crore in...

ED attaches 31 immovable properties worth Rs 581.65 crore in...

The attached properties are in the form of land parcels situated in Goa, Kerala, Karnataka, Punjab, Tamil Nadu, Uttar Pradesh, Haryana, Jharkhand, Maharashtra, Delhi, West Bengal, Andhra Pradesh, and Rajasthan.

Read More
General News

Shinde on bomb threat emails to blow BSE, Vidhan Bhavan

Shinde on bomb threat emails to blow BSE, Vidhan Bhavan

Maharashtra Deputy Chief Minister Eknath Shinde stated that the threats were bogus, calling the Vidhan Bhavan safe and added that operations to tackle the issue are underway smoothly.

Read More
General News

Rohit Pawar meets Rahul Gandhi in New Delhi

Rohit Pawar meets Rahul Gandhi in New Delhi

During the meeting, Rohit Pawar shared all relevant files and details, with KC Venugopal and other Congress leaders also present. The NCP (SP) MLA informed that Gandhi reviewed the information carefully, demonstrating a strong understanding of aviation matters, and expressed concern upon learning that an FIR has not been registered in Maharashtra.

Read More
General News

Himachal Minister Vikramaditya Singh meets Nitin Gadkari

Himachal Minister Vikramaditya Singh meets Nitin Gadkari

The meeting revolved around accelerating key road, bridge and tunnel projects in Himachal Pradesh, strengthening all-weather connectivity and ensuring that the State's fragile hill areas receive robust and safe infrastructure support from the Union Government.

Read More
General News

Commercial LPG shortage hits hotels, restaurants

Commercial LPG shortage hits hotels, restaurants

A commercial LPG shortage is affecting hotels and restaurants nationwide, with many forced to suspend operations. The government has formed a three-member committee to address grievances and prioritise domestic LPG supply.

Read More
Home About Us Our Products Advertise Contact Us Terms & Condition Privacy Policy

Copyright © aninews.in | All Rights Reserved.