Supply-chain constraints may cap India's data centre capacity at 3 GW by 2030: Report

Execution bottlenecks and supply-chain constraints could significantly slow India's data centre (DC) capacity expansion, limiting operational capacity to around 3 gigawatts (GW) by 2030 despite industry announcements targeting more than 6 GW, according to an Axis Capital report.

ANI Aug 03, 2026 11:30 IST googleads

Representative Image (Photo/Reuters)

New Delhi, [India] August 3 (ANI): Execution bottlenecks and supply-chain constraints could significantly slow India's data centre (DC) capacity expansion, limiting operational capacity to around 3 gigawatts (GW) by 2030 despite industry announcements targeting more than 6 GW, according to an Axis Capital report.
The report noted that while India's installed data centre capacity currently stands at around 1.4 GW, publicly announced expansion plans appear overly optimistic in view of execution challenges.
"Publicly-announced capacity targets of 6-8GW by 2030 look inflated; the expert's realistic estimate is 3.4-3.6GW cumulative operational DC capacity by mid-2030. On a more conservative basis... only ~2.8GW is likely to actually be operational by then given execution constraints," the report said.
According to the report, the biggest hurdles are bottlenecks in the mechanical, electrical and plumbing (MEP) supply chain, limited availability of critical equipment and skilled manpower, and delays in obtaining power connections.
It said award-to-commissioning timelines typically stretch to 28-36 months, while supply constraints have worsened as multiple developers execute projects simultaneously.
"DG gensets effectively limited to three global brands (Caterpillar, Cummins, MTU) are usable for hyperscaler-grade builds, and all three are already booked out roughly two years ahead given how many players are building simultaneously," the report said.
Besides equipment shortages, EPC contractor capacity, manpower availability and power sanction timelines of around 18 months are also emerging as major constraints, the report added.
The report further noted that India's preference for vertical data centre construction due to land and floor space constraints makes projects more complex and lengthens execution timelines compared with horizontal facilities built in overseas markets.
Despite the near-term challenges, the long-term outlook remains positive. The report said India's data centre industry could witness a sharp increase in capacity over the following five years if currently announced projects are executed as planned.
"The expert sees potential for 7-8 GW of capacity by 2035, if currently announced projects materialize in full, though in the nearer term, a more realistic 2030 operational estimate remains closer to ~3 GW," the report added. (ANI)

Get the App

What to Read Next

Business

Semicon Day 1: Rs 1 lakh crore investment commitments, 16 MoUs

Semicon Day 1: Rs 1 lakh crore investment commitments, 16 MoUs

The first day of SEMICON India 2026 saw the government lay out a wider roadmap for the next phase of India's semiconductor programme, with around Rs 1 lakh crore in investment commitments, plans to create close to one lakh jobs and a series of agreements spanning chip manufacturing, materials, packaging, design and talent development.

Read More
Business

No external pressure over MDR decision: DFS

No external pressure over MDR decision: DFS

"The allegation that MDR has been introduced under any external influence is patently false and misleading," the Department said

Read More
Business

India semiconductor push entering commercial production phase,

India semiconductor push entering commercial production phase,

India’s semiconductor push is beginning to move into a commercial production phase, with companies expanding local manufacturing, bringing products to market and building domestic supplier networks, according to industry executives at SEMICON India 2026.

Read More
Business

Tata Trusts asks Tata Sons to explore options other than listing

Tata Trusts asks Tata Sons to explore options other than listing

Tata Trusts on Thursday asked Tata Sons to explore all available options other than listing, reiterating their opposition to the public listing of the holding company and stressing the need to preserve the structure of the Tata Group.

Read More
Business

US jobless claims fall to 196,000, lowest since mid-July

US jobless claims fall to 196,000, lowest since mid-July

Initial jobless claims in the United States fell to 196,000 in the week ended September 12, their lowest level since mid-July, according to data released by the US Department of Labor on Thursday, a day after the Federal Reserve raised interest rates by 25 basis points.

Read More
Home About Us Our Products Advertise Contact Us Terms & Condition Privacy Policy

Copyright © aninews.in | All Rights Reserved.