Bullet train: Intermediate tunnel made in Mumbai to expedite works

The Mumbai-Ahmedabad bullet train corridor has been making steady progress since work began in November 2021. The project initially faced delays due to challenges in land acquisition.

ANI May 27, 2024 14:51 IST googleads

Mumbai Ahmedabad bullet train project (Image: National High Speed Rail Corporation Limited)

Mumbai (Maharashtra) [India], May 27 (ANI): In order to accelerate works in the ongoing ambitious Mumbai-Ahmedabad bullet train project, an additional 394-meter intermediate tunnel has been made at Ghansoli in Mumbai. This new intermediate tunnel will help speed up the 21-km-long main tunnelling work between BKC and Shilphata, abutting the Thane creek.

The 26-metre-deep new terminal is 3.3 km long, and it will allow simultaneous access to create a 1.6 meter (approx.) tunnel on each side. For the main 21-kilometre-long tunnel, 16 km is dug using tunnel boring machines and the remaining 5 km will be done through New Austrian Tunneling Method, a release from National High Speed Rail Corporation Limited, the special purpose company undertaking the bullet train project said.

The excavation work for the intermediate tunnel was started on December 6, 2023 and the entire length of 394 meters has been excavated in a period of six months.

A total of 214 controlled blasts were carried out using 27,515 kg of explosives under the supervision of experts.

The dimension of the intermediate tunnel is such that it will provide direct vehicular access to the main tunnel during construction and operation and can also be used for the purpose of evacuation procedure in case of emergency.

The construction works for 21 km from Mumbai Bullet Train Station to Shilphata in Maharashtra are going on at a rapid pace. About seven km of this tunnel will be under the sea in Thane creek, an intertidal zone.

This is the first tunnel of its kind to be built anywhere in the country. The 21 km long tunnel will be a single tube tunnel with two tracks for the top and bottom tracks. Presently, 16 km of the tunnel are under construction at BKC, Vikhroli and Savli, using the tunnel boring machines. The bullet train will be able to move at a speed of 320km/hr inside the tunnel.

Railways Minister Ashwini Vaishnaw in March this year said that the much-awaited bullet train project will be ready by 2026, with services between Surat and Bilimora commencing initially.

The Mumbai-Ahmedabad bullet train corridor has been making steady progress since work began in November 2021. The project initially faced delays due to challenges in land acquisition.

Prime Minister Narendra Modi and his then-Japanese counterpart Shinzo Abe launched the project in Ahmedabad on September 14, 2017.

National High-Speed Rail Corporation Limited (NHSRCL) was incorporated on 12th February 2016 under the Companies Act, 2013 with the object of financing, constructing, maintaining and managing the High-Speed Rail Corridor in India.

The Company has been modelled as a 'Special Purpose Vehicle' in the joint sector with equity participation by the Central Government through the Ministry of Railways and two State Governments viz. Government of Gujarat and Government of Maharashtra.
As per the Joint Feasibility Study report of 2015, the project was estimated to cost Rs 108,000 crore, with an expected completion period of 8 years. (ANI)

Get the App

What to Read Next

Business

India Emerging as Stable Investment Anchor in Turbulent Global

India Emerging as Stable Investment Anchor in Turbulent Global

Mumbai (Maharashtra) [India], March 12: As military conflict in West Asia disrupts energy supplies through the Strait of Hormuz and global liquidity tightens, leading investors, policymakers and capital markets leaders gathered at IGF Mumbai 2026: Catalysing Capital to assess India's position in an increasingly fragmented global economy.

Read More
Business

Nandita Desai Unveils a Unique Painting Exhibition on Vintage

Nandita Desai Unveils a Unique Painting Exhibition on Vintage

New Delhi [India], March 12: There is something quietly powerful about a window... It neither confines nor escapes. It simply allows us to look, to pause, to breathe between inner and outer worlds. In The Painted Window, multi-award-winning contemporary artist Nandita Desai turns this everyday architectural element into the soul of her fifth solo exhibition, transforming vintage and handcrafted windows into luminous works of art. Running from 16th to 21st March 2026 at the Kamalnayan Bajaj Art Gallery, Nariman Point, Mumbai, the exhibition brings together 50 artworks - windows that look outward at the world, and inward at memory and quiet reflection.

Read More
Business

Kody Technolab Ltd. Launches Medigo Robot

Kody Technolab Ltd. Launches Medigo Robot

Ahmedabad (Gujarat) [India], March 12: Kody Technolab Limited today announced the launch of Medigo Robot, a health screening robot developed to enable rapid preventive health assessments and expand access to routine screening across healthcare, public, and institutional environments.

Read More
Business

Finkurve Financial Services Limited (Arvog)

Finkurve Financial Services Limited (Arvog)

Mumbai (Maharashtra) [India], March 12: Finkurve Financial Services Limited (BSE: 508954), among leading Tech-first Gold Loan NBFC, announced that the Company has crossed Rs. 1,035 crore+ in Assets Under Management (AUM) surged by nearly 10x compared to FY23, marking a significant milestone in the company's growth trajectory within India's secured lending ecosystem.

Read More
Business

Producer-Actor Adarsh Gunduraj Launches Trailer of ‘Calendar’

Producer-Actor Adarsh Gunduraj Launches Trailer of ‘Calendar’

New Delhi [India], March 12: The team behind the upcoming women-centric film Calendar unveiled the trailer during a press conference in Mumbai on March 12, 2026. They took the opportunity to share insights about the project and its concept with the media.

Read More
Home About Us Our Products Advertise Contact Us Terms & Condition Privacy Policy

Copyright © aninews.in | All Rights Reserved.